Last wind turbine of wind farm Tera Kora II completed

May 10th, the construction of the fifth and last wind turbine of our new wind farm Tera Kora II on Curaçao has been finished. The next step is the full mechanical and electrical completion of the wind farm. Two of the five turbines already produce renewable energy, the 3rd wind turbine will be connected onto the grid this week. Shortly after, the 4th and 5th turbine will follow.

Tera Kora II is a wind farm with turbines type Vestas V117. The total installed capacity is 17,25 MW, it can produce green energy equivalent to the yearly annual consumption of 20.900 families.